Capital Works Projects

Vernon continues to invest in infrastructure for a sustainable future

The City is investing $28.6 million into infrastructure projects in 2025. The 1.9% Infrastructure Levy, directed entirely and immediately to infrastructure, are now becoming visible, with ongoing significant and necessary rehabilitation and improvement projects, like those featured below.

2025 Capital Projects

Start Date End Date

19th Avenue Playground Renewal

The City of Vernon initiated a playground renewal project at 19 Avenue Park, located at 1904 19th…
Jul 7, 2025 Aug 18, 2025 View

2025 Okanagan Landing Sewer

The City of Vernon is working to extend its sanitary sewer collection system to un-serviced areas…
Jan 1, 2025 Dec 31, 2025 View

27th Avenue Rail Crossing Upgrade

The 27 Ave rail upgrade project is identified in the City’s Master Transportation Plan and includes…
View

32nd Avenue and 38th Street Reconstruction

Construction of the final phase of work for the project began on April 22, 2025. The project…
Apr 22, 2025 Jun 30, 2025 View

43 Avenue Corridor Improvement Project

The 43rd Avenue Corridor Improvement Project is part of the City of Vernon's 2025 to 2029 Five-Year…
Sep 1, 2025 Nov 1, 2026 View

46 Ave - Pleasant Valley Road to 20th Street Multi-Use Path

This project is the construction of a multi-use path connecting the previously constructed multi-…
May 6, 2024 May 30, 2025 View

Alexis Park Irrigation Renewal

The City’s Park Irrigation Renewal project is to renew high-risk and high-priority park facility…
Jul 7, 2025 Sep 8, 2025 View

Cummins Forcemain Replacement (Project # 2025-14)

The sanitary sewer force main in Marshall Field area is planned for replacement in 2025 due to…
Mar 1, 2025 Nov 28, 2025 View

Lake Access Projects

Introduction:Throughout numerous public participation initiatives and consultation for the Official…
Mar 13, 2023 Apr 26, 2028 View

Official Community Plan and Transportation Plan Review

The City of Vernon will be updating its Official Community Plan (OCP) and Transportation Master…
Jan 12, 2024 Dec 31, 2025 View

Pathway and park trail connections (2 sites)

Site 1 - The Valleyview Place to Commonage Trail project is new construction of an…
Apr 1, 2025 Oct 31, 2025 View

Polson Park Vernon Creek Naturalization Project

The City is working to naturalize Vernon Creek through Polson Park over 2 phases. Construction of…
Jun 2, 2025 Nov 30, 2025 View

Pottery Ravine Park Renewal

This project involves upgrading the existing playground structure and enhancing the park at Pottery…
Jun 16, 2024 Apr 30, 2025 View

Priority Drainage Improvements - Kokanee Rd, Eastside Rd, Smith Rd, Okanagan Landing Rd

The Priority Drainage Improvement project is an annually funded project to help manage emerging…
May 28, 2025 Nov 28, 2025 View

Rock Slope Stabilization Project

The Rock Slope Stabilization Project continues this summer. There will be intermittent 30-minute…
May 1, 2025 Sep 12, 2025 View

Roundabout: Pleasant Valley Road and 39 Avenue

Update September 15, 2025 The Pleasant Valley Road and 39 Avenue roundabout is complete, and roads…
Mar 10, 2025 Sep 12, 2025 View

Roundabout: Silver Star Road and Phoenix Drive

August 2025 update: As we round the corner into August, so does the roundabout construction of the…
Apr 22, 2025 Sep 30, 2025 View

Sawicki Playground Renewal

The City of Vernon is initiating a playground renewal project at Sawicki Park, located at 996…
Jul 8, 2025 Sep 30, 2025 View

Transportation Safety Improvements

This project will perform safety improvements to intersections and construct crosswalks on roadways…
Mar 18, 2024 Nov 29, 2024 View

Water Reclamation Plant Bank Armoring

Project Overview The Vernon Water Reclamation Centre (VWRC) Bank Armouring portion of the VWRC…
Jul 28, 2025 Oct 31, 2025 View