PRIORITY DRAINAGE IMPROVEMENT BX CREEK CROSSING AT 42nd AVENUE

Funded by
1.9 % Infr. Levy
Project State
Current

The Project consists of rehabilitating approximately 21m of a 2.2m diameter deteriorating storm culvert that contains BX Creek. A Geopolymer spray on coating will be applied to the inside of the culvert. BX Creek will be temporary bypassed during the spray on application process. The project is expected to take 4 weeks to complete. 