Capital Works Projects

Building a Better Vernon, Together!

 

Council Continues To Invest In Vernon’s Infrastructure

Showing Council’s commitment to renewing the roads, pipes and all City owned infrastructure. The impacts of the 1.9% cumulative infrastructure levy, directed entirely and immediately to infrastructure, are now becoming visible throughout the City with $12 million being spent on rehabilitation and improvements in 2018. The larger projects for 2018 include:

• the 30th Street and 35th Avenue project that will make a significant connection of 30th Street and 35th Avenue for pedestrians, cyclist and vehicles;

• advancement of the Okanagan Landing Sewer Extension through the completion of the CWWF; and

• the 32nd Avenue Road and Utility Reconstruction (29th to 30th Street) Project that will renew a key arterial road through the City Center and complete the removal of utilities in the Vernon Block.

Twenty smaller but equally important renewal and reconstruction projects round out the 2018 Capital Project list.

Start Date End Date

28TH AVENUE ROAD AND UTILITY REHABILITATION PROJECT

Reconstruction is required on 28th avenue from 30th street to 32nd street due to poor condition of...
Oct 30, 2018 Jun 28, 2019

View

29th Avenue Road and Utility Rehabilitation Project

UPDATE JUNE 4, 2018: This project is now complete and the road is open. UPDATE: Construction has...
Mar 5, 2018 May 25, 2018

View

30 avenue BX Creek Crossing rehabilitation

This project includes installing concrete head wall, re-lining the existing culvert and modifying...
Sep 12, 2019 Oct 31, 2019

View

30 Street Phase 2 - 30 Avenue to 34 Avenue

UPDATE: 30 Street including the intersection of 30 Street and 32 Avenue is now open with 32 Avenue...
Jun 26, 2017 Jun 2, 2018

View

30TH STREET/35TH AVE ROAD AND UTILITY REHABILITATION

UPDATE: Project is scheduled to be complete the week of October 8. UPDATE: 35th Avenue adjacent to...
Apr 23, 2018 Oct 12, 2018

View

32ND AVENUE RECONSTRUCTION

UPDATE: The project is scheduled to be complete the week of October 8. UPDATE: Access route maps ...
May 21, 2018 Oct 12, 2018

View

Kalamalka Lake Road Transportation Project - Coldstream Border to Browne Road

Phase two construction of DCC Project TR24 - Kalamalka Lake Road Multi Use Path from Browne Road to...
Mar 26, 2018 Jul 16, 2018

View

OKANAGAN AVENUE DRAINAGE UPGRADES - CONTRACT #2 STORMWATER FACILITY

Please be advised the R.L. Walker, on behalf of The City of Vernon is scheduled to start...
Jan 1, 2018 Dec 31, 2018

View

Okanagan Landing Sewer Extension

Extension of sanitary sewer to several unserviced areas in the Okanagan Landing area.
Aug 14, 2017 Nov 30, 2018

View

Pottery Road Rehabilitation - 15 Street to City Border

Rehabilitation of the Pottery Road due to failed condition. Project will include rehabilitation of...
Oct 2, 2017 Oct 13, 2017

View

Priority Sidewalk Program - 24 Ave from 39 Street to 43 Street

New sidewalk on 24th Avenue from 39th Street to 43rd Street. The project was identified as a high...
Aug 3, 2017 May 4, 2018

View